Tubular vs Open-Width: The Real Cost Difference

Tubular knitting plus outsourced slitting against an open-width machine: the per-1,000-metre cost build, the break-even volume, and when the answer flips.

If you outsource slitting, an open-width machine usually pays for itself within months. On the cost build below, the tubular route lands near $359 per 1,000 metres of saleable fabric and the open-width route near $229 — about $0.13 a metre, against a capital premium of roughly $5,000. The instinct that open-width is expensive survives only in mills that already own a slitting line, or sell tubular rolls by design.

Cost per 1,000 Metres Is the Only Fair Unit

Machine quotes arrive per unit, yarn per kilo, slitting per metre, seconds as a percentage of value. Without a common denominator, a $4,000 saving on capital becomes a five-figure annual loss. Fix the unit at 1,000 metres of saleable open-width fabric.

All figures are indicative for Q4 2026, quoted in USD, and rest on one assumption set you should overwrite with your own:

  • Fabric: single jersey, 180 g/m², 1.60 m usable width, so 1,000 m equals 288 kg of greige. Heavier structures such as double jersey raise the per-metre weight and scale every line below.
  • Output: 22 kg per machine hour, which is about 76 m per hour at that weight.
  • Machine: 34 inch, 24 gauge. Tubular unit at $24,000, open-width unit at $29,000, five-year straight-line depreciation over 6,000 running hours a year.
  • Conversion hour rate: $13.70 tubular, $14.50 open-width, covering power at $0.12/kWh, one operator across six machines at $3.50/hour and overhead. Depreciation sits on its own line so it can be stripped out.
  • Greige value $4.50/kg. Crease and needle-line seconds 2.5% tubular against 0.8% open-width. Edge trim 1.2% against 0.4%. Slitting job work $0.11/m, the middle of a $0.08–0.14/m band in Asian textile hubs.

Cost Build: Tubular Plus Slitting vs Open-Width

Both routes knit the same fabric. The difference is everything after the needle cylinder, and that is where the money moves. Figures are USD per 1,000 m.

Line itemTubular + outsourced slittingOpen-width machine
Knitting conversion (power, labour, overhead)179190
Machine depreciation (5 years, 6,000 h/yr)1014
Slitting or opening11010
Edge trim loss (1.2% vs 0.4%)165
Crease and needle-line seconds (2.5% vs 0.8%)3210
Extra handling and internal transport120
Total per 1,000 m359229

The capital premium is not the story. Five thousand dollars of extra machine, spread over five years and 30,000 running hours, costs about $4 per 1,000 metres — invisible beside the $100 slitting bill. What the open-width machine actually buys is the removal of a process step that carries a per-metre charge, a trim loss, and a crease risk that only surfaces after dyeing. If you want the wider cost architecture these lines sit inside, our regional TCO comparison breaks the same numbers down by machine origin.

The Break-Even Volume Formula

Because the gap is a cash gap, test it against the capital premium rather than against a depreciation schedule:

V* = ΔCapex ÷ (Ctubular − Copen), where both C terms are cash cost per metre with depreciation excluded.

Worked example from the table: cash costs are $349 and $215 per 1,000 m, a difference of $134, or $0.134/m. With ΔCapex of $5,000, V* = 5,000 ÷ 0.134 ≈ 37,300 m. At 76 m/h that is roughly 490 machine hours — about ten weeks on one shift, three to four weeks on three.

At the other end of the bands the threshold moves: a $9,000 premium against a $70 gap puts V* at 129,000 m, most of a year of single-shift output on one machine.

Eight Rows That Decide the Question

DimensionTubular + slittingOpen-width machine
Builders and diameter rangeWide: 30–38 inch, many sources, short lead timeNarrower: fewer builders, 30–36 inch typical
Extra process stepSeparate slitting line or job work, plus transportIntegrated opening, single pass
Crease exposure before finishingHigh: plaited rope form, pressure folds in storageLow: flat fabric, low-tension winding
Indicative capex, 34 inch$22,000–28,000$26,000–34,000
Power per machine hourBaseline8–15% higher
Edge trim1.0–1.5%0.3–0.6%
Handling per 1,000 mOne extra pass, 0.3–0.5 hourNone beyond take-down
Product fitTubular garment, trims, cuffs, tubular technicalsCut-and-sew knits, print, compressive finishing

Apply the thresholds in order. A cash gap above $90 per 1,000 m: buy open-width, payback lands inside two months of single-shift output. A gap of $40–90: buy it only if annual output on that machine clears roughly 150,000 m. Below $40: stay tubular and spend the effort on the slitting rate, where a $0.03/m concession beats a machine discount.

Who Should Buy Which

Buy open-width if slitting is currently outsourced, if your fabric is crease-sensitive after dyeing or compacting, or if your customer measures width and bow at the finished roll. Structures that must stay dimensionally stable across the full width, interlock above all, benefit most — the same crossover our interlock versus rib costing measures on the machine side.

Stay tubular if you already run a slitting line with spare capacity, if you supply tubular garment makers or trim producers, or if your order book mixes structures where one open-width head would sit idle half the week. A merchant converter with a broad catalogue often finds the extra handling cheaper than the extra capital.

Buy tubular plus an in-line slitter as the middle path: a slitting attachment adds a small fraction of a machine price and removes the separate transport pass, but leaves the crease risk, so it suits plain structures.

When This Conclusion Reverses

The arithmetic is a cash comparison, and four conditions break it.

  • Your slitting is already in-house at near-zero marginal cost. If the line is depreciated and staffed for other reasons, the $110 entry collapses toward $20 and the case narrows to trim and crease seconds. Below a $40 gap, the premium stops earning.
  • Your customer buys tubular. Slitting destroys the product for tubular garment, cuff and trim buyers, and no model rescues a fabric the buyer cannot use.
  • Volume per machine is low. Below roughly 50,000 m a year on a dedicated head, the open-width unit idles too much for V* to arrive.
  • Capital is expensive or the currency moves. A $5,000 premium financed at 12% costs about $600 a year before any output, and a 5% swing on a machine invoiced in EUR or USD makes the premium itself a moving target — the same logic behind our flat versus circular comparison.

Crease losses surface only after finishing, so a mill selling greige in rope form never records them and will overvalue the tubular route; if reject reports carry no crease cause code, measure three lots first. Past a certain volume the cheaper route may not be open-width at all but another process, which our circular versus warp analysis prices out.

FAQ

Is an open-width machine just a tubular machine with a slitter?
No. A slitter cuts a knitted tube along a crease line, leaving an edge and a needle line to manage. An open-width machine opens the fabric as it is knitted, which is why trim loss and crease exposure both fall, but builders and diameter options are fewer.

How much does outsourced slitting cost per metre?
Indicative $0.08–0.14/m in major Asian textile hubs for plain single jersey, before transport and handling. Sensitive or high-gauge fabric sits at the top of the band because the line runs slower.

Can I retrofit an opening unit to a tubular machine?
Often yes, as a factory-fitted option or a field kit, at a fraction of the price difference between machine types. It removes the extra transport pass but leaves most of the crease risk, so check what the quote actually includes.

Does open-width reduce weight variation across the roll?
It reduces one source of it, because the fabric is not plaited and compressed before finishing. Yarn and feed variation still dominate, so treat width uniformity and weight uniformity as separate measurements.

Which fabric should never be converted?
Tubular product sold as tubular, and structures where the buyer specifies a tube width. Converting those to open width adds a process and removes the only feature the customer is paying for.

How do I count crease seconds honestly?
Add a crease cause code to the finishing reject sheet, run three lots of each route, and compare against saleable metres rather than against knitted metres. Without that code the loss lands in a general seconds bucket and the comparison quietly disappears.