Demurrage and Detention: Who Pays for the Delay

Demurrage and detention cost USD 60-260 per container-day. See who pays under FOB, CFR and DDP, the free-time formula, and the documents that win a waiver.

A 40-foot high cube held nine days past free time adds USD 900–1,600 to a USD 26,000 FOB machine — 3.5–6% of its value — and the carrier bills the consignee, not whoever caused the delay. Both clocks are cheaper to remove before the vessel sails.

Two Clocks, and What Each Costs

Demurrage is charged while the container sits inside the terminal, after the free days following discharge expire. Detention is charged while it is outside the terminal and not yet returned empty. Separate tariffs on separate clocks — one negotiated figure for “port charges” always leaves money on one side.

The start date matters more than the rate. Demurrage begins at discharge, not at vessel arrival or the arrival-notice date: a late Friday discharge consumes two of five free days before a broker opens the file on Monday. Detention begins at gate-out under merchant haulage, or at discharge under carrier haulage. Customs delays land on demurrage, foundation and crane delays on detention — so fix the clock your own process controls.

ChargeIndicative per 40HQ-dayClock startsInvoiced by
Demurrage, tier one (days 1–5 chargeable)USD 90–150Day after free time expires from dischargeCarrier or terminal
Demurrage, tier two (day 6 onward)USD 150–260Same clock, escalating bandCarrier or terminal
Detention, empty return overdueUSD 60–130Day after free time expires from gate-outCarrier or container owner
Terminal storage after the demurrage capUSD 25–60 per cbm-weekWhen the box is moved off-dockTerminal or depot
Crane and crew standby on siteUSD 250–500When a booked slot is missedRigging contractor
Prime mover or chassis standbyUSD 120–300Per re-booked haulage slotHaulage company

Rates are indicative for Q4 2026 in USD; tariffs escalate by tier and vary by port, so use the page printed at booking. Freight is a separate line, in this import duty and shipping cost guide. The tier jump is the trap — day six costs about twice day one — and past day four a bonded warehouse is usually cheaper than the clock.

The Formula That Turns Free Time into a Budget

Price the delay the way you price the machine, before the deposit leaves:

Delay cost = (Ddem × Rdem) + (Ddet × Rdet) + (Cstandby × Dstandby) + Lfin

Ddem is chargeable demurrage days at tiered rate Rdem; Ddet detention days at Rdet; Cstandby idle crane and crew per day; Lfin financing cost of money already paid for an idle machine.

Worked example: one 40HQ, FOB USD 26,000, free time 5 days demurrage and 7 detention. Discharge 3 November, release 10 November after origin verification, empty returned 19 November because the foundation is not ready.

  • Demurrage = 10 − 3 − 5 = 2 days × USD 120 = USD 240
  • Detention = 19 − 10 − 7 = 2 days × USD 85 = USD 170
  • Standby, two re-booked crane slots × USD 350 = USD 700
  • Total = USD 1,110, or 4.3% of FOB

Stress the base case: three more terminal days push demurrage into tier two at USD 200, turning USD 240 into USD 600. That sensitivity is what you hold in reserve — the same arithmetic that governs freight timing in this sea freight guide for textile machinery.

Who Pays Under FOB, CFR and DDP

The Incoterm decides who contracts the carriage, not who absorbs delay. The carrier bills the party on the bill of lading, which recharges under the contract; where the two disagree, the carrier wins.

TermFreight booked byDestination demurrageDestination detentionDeciding clause
FOBBuyerBuyer, as consigneeBuyerConsignee named on the bill of lading
CFR / CIFSellerBuyer, unless liner terms all-inBuyerFreight prepaid excludes delay charges
DAPSellerSellerBuyer beyond the unloading windowUnloading free time, usually 4–6 hours
DDPSellerSellerSeller, unless return is assigned to buyer in writingNamed place plus written return duty

Under FOB and CFR you own both clocks, so negotiate free time with the carrier at booking, not the supplier. Under DAP and DDP the seller owns them and recovers the cost inside the machine price — the arithmetic this import cost calculator walkthrough is built to expose. Origin files matter as much: a missing certificate becomes terminal days, not a smaller invoice, as the Vietnam duty structure and VAT reduction checklist both show.

Documents That Decide Who Pays

In a dispute the carrier asks for evidence, not explanation. Keep this file per shipment; complete documents cut release time by one to three days.

DocumentHeld byDelay it preventsValue in a waiver request
Timestamped arrival noticeCarrier agentLate customs lodgementProves when notification reached you
Bill of lading, original or telexBank or shipperNo delivery order without itShows whom the carrier may bill
Delivery order and interchange receiptBuyer or haulierGate-out and damage disputesFixes the gate-out date
Entry, invoice, packing list, origin certificateBrokerHeld entry, inspection referralShows the delay was authority-driven
Tariff page and booking confirmationBuyerWrong-tier or inflated billingOnly proof of your agreed free days
Crane and rigging booking confirmationBuyerStandby charges on both sidesShows mitigation was already booked

Three Levers That Remove Most of the Exposure

Lodge the entry before arrival, one person-day. With manifest, invoice, packing list and origin certificate five days before ETA, most brokers pre-clear and release on the discharge date — one to three chargeable days saved.

Negotiate free time at booking, one week once. Ask for 14 days demurrage and 14 days detention on capital equipment; carriers grant it selectively at USD 100–250 per container, still cheaper than four tier-two days. Keep the tariff page — free days exist only if you can produce them.

Sequence trucking after unloading, one person-day. Book the crane for the day after a confirmed gate-out with a 48-hour re-book clause, and return the empty the day the machine leaves the trailer. Detention is nearly always self-inflicted; the loading and return plan belongs in the pre-shipment evidence file, as in this supplier audit checklist for China.

When This Conclusion Reverses

Paying to remove the risk is not always rational:

  • Exposure under one day. One tier-one day at USD 90–150 is cheaper than the USD 300-plus carriers charge to extend free time on a two-container booking.
  • Output value exceeds the rate. If a commissioned machine earns USD 1,200 a day in contribution, USD 120 to protect the schedule is correct. Demurrage is only expensive against idle capacity.
  • The delay is structural. Where port dwell averages over ten days, free-time negotiation stops working; change gateway or take carrier haulage with an all-in window.
  • Small freight, critical parts. For a crate of needles, air freight can beat sea freight plus storage — but the deciding number is line-down cost, not the invoice.

Currency flips the model too. Figures are USD at a Q4 2026 band of CNY 7.10–7.25 per USD; a swing beyond 3% moves standby and rigging lines more than demurrage, so re-run at your settlement rate before signing DDP.

FAQ: Demurrage, Detention and Delay Cost

What is the difference between demurrage and detention?
Demurrage runs while the container is inside the terminal beyond free time; detention runs while it is outside and not yet returned empty. Separate tariffs, separate clocks — budget and negotiate them independently.

When does the demurrage clock start?
At discharge, not at arrival or the notice date. A late or weekend discharge eats free days before any customs file exists, which is why pre-lodging the entry is the strongest control.

Who pays under FOB terms?
The buyer, as consignee on the bill of lading. Under CFR and CIF destination delay stays with the buyer unless the contract grants liner terms all-in; under DAP and DDP the seller carries it and prices it back in.

How much free time should I request?
14 days demurrage and 14 days detention on 40HQ capital equipment, against a market default of five to seven. Expect USD 100–250 per container if granted, and keep the written grant.

Can demurrage be waived?
Sometimes, with evidence that the carrier, terminal or customs authority caused the delay: arrival notice, entry lodgement, inspection referral, interchange receipt. Treat goodwill waivers as a bonus, never a plan.

Does DDP remove demurrage risk?
Not automatically. The seller bears delivery to the named place, but the empty-return duty can sit with whoever holds the container. Assign the return obligation in the contract, not only in the Incoterm.